In the past month of interviews, I’m seeing ‘project coordinator’ postings expect full schedule control and resource loading without real authority to negotiate scope or fees. On my last 32‑week civic renovation in Seattle, I ran the MS Project critical path and aligned consultant milestones to permitting windows, but it only held with principal-level backing — are firms shifting schedule ownership away from PMs, or is this just a title/comp shell game?